When Should Builders Risk Insurance Be Purchased?
Arrange it before the coverage is needed—ideally before materials arrive or work begins—and confirm the insurer has bound coverage for the correct start date.
Buyers should start the insurance discussion while planning the project and obtain a bound policy before the first relevant property exposure. Builders risk addresses construction-stage property, and the NAIC definition includes buildings in the course of construction plus certain materials and equipment. A quote request alone does not mean the policy has taken effect.
The date may need to precede ground-breaking if building materials will be stored or delivered earlier. US Assure’s application guidance asks applicants to address policy timing and construction stage; its program also requires additional review for submissions made after a stated completion threshold. That threshold applies only to its program.
Give the insurer the expected delivery date, work start, completion percentage, project schedule, and requested policy term. Confirm binding, effective date and time, covered locations, and any underwriting conditions in writing. Coordinate the start with the construction contract and any existing property insurance.
Related Coverage
Sources
- Glossary of Insurance Terms. National Association of Insurance Commissioners; Builders’ Risk Policies. Accessed 2026-09-25.
- Builders Risk Coverage Form. Insurance Services Office, Inc.; hosted by Touchpoint Markets; IH 00 70 05 17, copyright 2017 (illustrative specimen): A.1–3, printed pp. 1–2; B, printed pp. 9–11; C–E, printed p. 12. Accessed 2026-09-25.
- Builders Risk Application Tip Sheet. US Assure; General policy application tips, p. 1; Remodeling policy application tips, p. 2. Accessed 2026-09-25.